20:10:36:14Multiple interconnections.
Section · Administrative Rules of South Dakota · View on sdlegislature.gov ↗
Rulemaking activity
- ARSD 20:10Noticed
- ARSD 20:10Effective
- ARSD 20:10Effective
The public utility may propose to interconnect more than one small generator facility at a single point of interconnection in order to minimize costs, and may not unreasonably refuse a request to do so. However, an applicant or an interconnection customer may elect to pay the entire cost of separate interconnection facilities.
Source: 35 SDR 305, effective July 1, 2009.