20:10:36:23Study deposit.

Section · Administrative Rules of South Dakota · View on sdlegislature.gov ↗

Rulemaking activity

The public utility may require a deposit of no more than 50% of the cost estimate for all studies. However, the deposit may not exceed $1,000 for small generator facilities proposing to interconnect 500 kilowatts or less. The deposit shall be paid in advance by the applicant for studies necessary to complete an interconnection to the EDS.

Source: 35 SDR 305, effective July 1, 2009.