20:10:36:40Tier 2 application completion.
Section · Administrative Rules of South Dakota · View on sdlegislature.gov ↗
Rulemaking activity
- ARSD 20:10Noticed
- ARSD 20:10Effective
- ARSD 20:10Effective
The tier 2 interconnection process is complete when: (1) All tier 2 screening criteria are satisfied and any minor EDS modifications are implemented; (2) The small generator facility installation is approved by an electric code inspector with jurisdiction over the interconnection; (3) The witness test, if conducted by the public utility, is successful; (4) The parties execute a certificate of completion; and (5) An interconnecting agreement has been executed.
Source: 35 SDR 305, effective July 1, 2009.