20:10:36:49Tier 3 interconnection completion.

Section · Administrative Rules of South Dakota · View on sdlegislature.gov ↗

Rulemaking activity

The tier 3 application process is complete when: (1) All tier 3 screening criteria are satisfied and any minor modifications to the EDS that may have been identified are implemented; (2) The small generator facility installation is approved by an electric code inspector with jurisdiction over the interconnection; (3) There is a successful completion of the witness test, if required; (4) The parties execute a certificate of completion; and (5) An interconnection agreement has been executed.

Source: 35 SDR 305, effective July 1, 2009.