20:10:36:56Optional tier 4 interconnection system impact
Section · Administrative Rules of South Dakota · View on sdlegislature.gov ↗
Rulemaking activity
- ARSD 20:10Noticed
- ARSD 20:10Effective
- ARSD 20:10Effective
study results meeting. The public utility shall contact the applicant to schedule an optional tier 4 interconnection system impact study results meeting to review the interconnection system impact study report and discuss the identified interconnection facilities and system upgrades. The parties may also mutually agree to adjust the study timeline determined at the scoping meeting based upon the interconnection system impact study results.
Source: 35 SDR 305, effective July 1, 2009.