20:10:36:70Temporary disconnection due to unauthorized

Section · Administrative Rules of South Dakota · View on sdlegislature.gov ↗

Rulemaking activity

equipment modifications. If the interconnection customer makes any change other than minor equipment modifications without prior written authorization of the public utility, the public utility has the right to temporarily disconnect the small generator facility from the utility's EDS at any time and for as long as reasonably necessary.

Source: 35 SDR 305, effective July 1, 2009.