50:02:01:17Time limits.

Section · Administrative Rules of South Dakota · View on sdlegislature.gov ↗

Projects which are receiving state assistance must adhere to the following time limits. All times refer to days after the declaration of an emergency or disaster by the Governor. Work Initiation Completion Category of Work of Work (1) Debris clearance 30 days 180 days (2) Emergency measures 30 days 180 days (3) Permanent work 18 months The time limits imposed by §§ 50:02:01:15 and 50:02:01:16 and this section may be extended by the director of the Division of Emergency Management for up to six months if requested and justified in writing by the applicant. Justification must be based on extenuating circumstances beyond the control of the applicant.

Source: 20 SDR 189, effective May 15, 1994.