74:27:08:05Presubmission

Section · Administrative Rules of South Dakota · View on sdlegislature.gov ↗

meetings. An applicant proposing to construct a new Type I or IIA facility shall schedule a presubmission meeting with the secretary at least 30 days before submittal of the Phase I application. Other applicants may schedule meetings with the secretary to discuss general and technical application requirements, including the site characterization required by chapter 74:27:12, in advance of permit application preparation.

Source: 17 SDR 8, effective July 26, 1990; 19 SDR 186, effective June 10, 1993.