74:27:08:12Permit application --

Section · Administrative Rules of South Dakota · View on sdlegislature.gov ↗

Completeness review. The secretary shall conduct a completeness review of each permit application received as follows: (1) Within 90 days after submission of an application or amendment for a Type IIB, III, or IV facility, within 90 days after completion of a Phase I application for a Type I or IIA facility, or within 30 days after submission of a renewal, the secretary shall notify the applicant in writing whether the application is complete; (2) If the application is incomplete, the secretary shall identify the items required to complete the application; and (3) The secretary shall determine the adequacy of the applicant's response to each incomplete item within 15 days after receipt of the response.

Source: 17 SDR 8, effective July 26, 1990; 19 SDR 186, effective June 10, 1993; 20 SDR 56, effective October 24, 1993.