74:36:05:15Deadline for final
Section · Administrative Rules of South Dakota · View on sdlegislature.gov ↗
Rulemaking activity
action on permit application. Except for the permitting of affected sources under the Title IV acid rain program, final action on each permit application for an operating permit for a Part 70 source, including requests for permit modification or renewal, must be completed within 18 months after receipt of a complete application.
Source: 19 SDR 157, effective April 22, 1993; 21 SDR 119, effective January 5, 1995.