Skip to main content
Login

74:55:01:04Date of application for new wells.

Section · Administrative Rules of South Dakota · View on sdlegislature.gov ↗

Operators of a new injection well shall submit a complete application at least 270 days before the date construction is expected to begin unless the new well is covered by an area permit.

Source: 8 SDR 71, effective December 24, 1981; 13 SDR 129, 13 SDR 141, effective July 1, 1987; transferred from § 74:03:11:04, July 1, 1996; 34 SDR 279, effective May 12, 2008.