The Public Utilities Commission can now charge large data centers (those using at least 10 megawatts of power) for the actual costs of reviewing and processing their special electric service contracts. Any fees collected will go into the state's Public Utilities Commission fund to support its operations.
Signed by the Governor H.J. 579
Delivered to the Governor H.J. 574
Signed by the President S.J. 528
Signed by the Speaker H.J. 560
House of Representatives Concurred in amendments Passed, YEAS 67, NAYS 0. H.J. 548
Senate Do Pass Amended Passed, YEAS 32, NAYS 2. S.J. 494
Commerce and Energy Do Pass Amended Passed, YEAS 7, NAYS 2.
Commerce and Energy Motion to amend
Commerce and Energy Scheduled for hearing
Commerce and Energy Scheduled for hearing S.J. 1
First read in Senate and referred to Senate Commerce and Energy S.J. 170
House of Representatives Do Pass Amended Passed, YEAS 60, NAYS 5. H.J. 196
Commerce and Energy Do Pass Amended Passed, YEAS 12, NAYS 0. H.J. 11
Commerce and Energy Motion to amend H.J. 11
Commerce and Energy Scheduled for hearing
First read in House and referred to House Commerce and Energy H.J. 11
Concurred in amendments
Do Pass Amended
Commerce and Energy — Do Pass Amended
Do Pass Amended
Commerce and Energy — Do Pass Amended