This bill creates new rules requiring electric utilities to charge data centers the full cost of providing them electricity, including any infrastructure upgrades needed to serve them, rather than spreading those costs to other customers. The bill also prevents data centers from leaving other customers responsible for paying stranded costs if the data center shuts down early or for decommissioning expenses. These rules apply to all data centers, with special definitions for "large data centers" using 20 megawatts or more of electricity.
State Affairs Deferred to the 41st legislative day Passed, YEAS 10, NAYS 2.
State Affairs Scheduled for hearing
House of Representatives Referred to House State Affairs H.J. 237
First Reading House H.J. 220
Prime sponsor · Rep.
D
Cosponsors
State Affairs — Deferred to the 41st legislative day