20:10:36:05Commissioning or operation notice.
Section · Administrative Rules of South Dakota · View on sdlegislature.gov ↗
Rulemaking activity
- ARSD 20:10Noticed
- ARSD 20:10Effective
- ARSD 20:10Effective
A public utility shall require the applicant to provide commissioning notice or notice of intent to begin operations of a small generation facility to the public utility. A tier 1 application shall provide 10 business days notice. A tier 2, tier 3, or tier 4 application shall provide 20 business days notice.
Source: 35 SDR 305, effective July 1, 2009.