20:10:36:07Term of interconnection.
Section · Administrative Rules of South Dakota · View on sdlegislature.gov ↗
Rulemaking activity
- ARSD 20:10Noticed
- ARSD 20:10Effective
- ARSD 20:10Effective
Interconnection of a small generator facility is considered to be in effect for a period of up to 20 years at the interconnection customer's option, unless terminated earlier by the default or voluntary termination by the interconnection customer or by action of the commission. Any interconnection agreement entered into before the effective date of this rule shall remain in effect until the term of the agreement expires.
Source: 35 SDR 305, effective July 1, 2009.