The public utility may not unreasonably refuse to grant an expedited review of a request to renew an interconnection agreement. If the conditions on the EDS are essentially the same as when the agreement was originally approved, the public utility may waive all or part of the application fee if fewer expenses are incurred in renewing the application, provided that the facility has not undergone anything other than minor equipment modifications, as determined by the public utility, since the expired agreement was approved.
Source: 35 SDR 305, effective July 1, 2009.