44:75:01:08Plans of correction.

Section · Administrative Rules of South Dakota · View on sdlegislature.gov ↗

Within ten days of the receipt of the statement of deficiencies, each licensed facility must submit to the department a written plan of correction for the citation of noncompliance with licensure requirements. The plan of correction must be signed, dated, and on the original forms provided by the department. The department may reject the plan of correction if there is no evidence the plan will cause the facility to attain or maintain compliance with SDCL chapter 34-12 and this article.

Source: 42 SDR 51, effective October 13, 2015; 50 SDR 62, effective November 27, 2023.

General Authority

Law Implemented